4: Foundations Part 1
After yesterdays site scrape the ground workers started again at 07:00 this morning (22nd August 2018) to dig the trenches for the foundations.
The idea was to dig the trenches today and then pour the concrete tomorrow. However whilst I was at work around 16:00 the local friendly drone guy sent me a couple of photos which looked like there was concrete in the trenches - this was a nice surprise.
Tomorrow 1 of the brickies (the other 2 are on holiday) is going to start the under building (foundation walls), they estimate that this will take 3 days.