SAP Completion and other bits and pieces needed

Featured Replies

We waved goodbye to our Principle Designer at an earlier stage of the build and we are now approaching completion and lining things up for BC completion sign-off. Is there are a definitive list of reports and tests that we will need for this? We have kept BC aware of design changes and agreed the various SAP and build estimated reports that we would build to as we have gone along, but now wondering for example if we are going to need an airtightness test and final SAP report for completion? (We used Aerobarrier, so have a final result from them regarding air tightness, but not sure whether this would be valid for BC???) 

 

Any ideas and input very welcome. 

You airtightness after second fix for building control. You also need an as built SAP completed.

BC won’t care about any design changes Only that followed building regs 

 

Gas 

Electric 

Boiler- HP certificate 

Sap completion 

Which you can do by email which any number of online Sap assessors 

and just a general walk round Disabled access Glass Drains if they haven’t been checked already 

If it’s like Scotland the form includes a list of stuff you need. I had to submit an amendment to the warrant detailing all the changes we made that differed from the warrant prior to completing the approval certificate. 
 

Well done in getting this far. Nearly there! 

Edited by Kelvin

9 minutes ago, Kelvin said:

If it’s like Scotland

And a home owners manual

1 minute ago, JohnMo said:

And a home owners manual


And the sustainability certificate pinned to the wall. 

The easiest is not to second guess BC. Get them around to do the final inspection and ask them what reports/certificates they will need to issue a completion certificate. It will include an as built SAP which needs a feed in figure from an airtightness test but some ask for flow rates from extracts etc, etc. Just get a list and tick them off as you collect them and forward the lot on as a job lot.

I am doing one of these at the moment.  A fair amount of paperwork but just be methodical.  Best to do in one lot if you can.

  • Author

Thanks all. That is superb, we have been fairly organised so far, and to the fair the BC guys have been very good to date, I'm just itching to get sign-off!

 

Create an account or sign in to comment

Account

Navigation

Search

Search

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.