Norbert Posted May 5 Share Posted May 5 We have planning permission. It involves demolition and rebuilding on more or less the same footprint. We have 3 years to commence the work. How can we preserve the permission in perpetuity without actually commencing demolition if we choose to delay? One option would appear to be to replace the existing outdated/illegal septic tank with a new package treatment works, which was included in the plans as a necessary condition to get permission. Plus of course it is the right thing to do anyway. So would doing this constitute a start that would be acceptable (I presume it would) How do we document that this start has been made and therefore PP will last indefinitely, possibly for use by a future buyer? Do we need to get our plans agreed with Building Control before we we start on the new package treatment works? Do they then need to inspect the installation and sign that off as proof of anything? Any advice on this would be very welcome Link to comment Share on other sites More sharing options...
DevilDamo Posted May 5 Share Posted May 5 You’ll find this of some use… https://www.adpltd.co.uk/our-knowledge/what-counts-as-commencement-of-development#Legal Requirements for Commencement of Development In order to confirm commencement, you can look to submit a Lawful Development Certificate to the LPA. The definition of a Planning commencement is different to a Building Regulation commencement. Link to comment Share on other sites More sharing options...
twice round the block Posted May 5 Share Posted May 5 We spoke to building control and they we're happy for us just to put the new drain runs in. Obviously every local authority and every application is different on what is acceptable to them. You'll just have to contact them. Link to comment Share on other sites More sharing options...
DevilDamo Posted May 5 Share Posted May 5 @twice round the block Apart from the OP is asking about Planning, not Building Regulations. 1 Link to comment Share on other sites More sharing options...
Alan Ambrose Posted May 6 Share Posted May 6 Note that there’s a CIL gotcha here if this is self-build and your LPA charges CIL - that is that you/your buyer won’t be able to apply for planning for a new design and get a self-builld CIL exemption. That’s because you have already started on this development. Link to comment Share on other sites More sharing options...
Norbert Posted May 6 Author Share Posted May 6 Thanks all. My LPA does not charge CIL Link to comment Share on other sites More sharing options...
DevilDamo Posted May 6 Share Posted May 6 3 hours ago, Alan Ambrose said: That’s because you have already started on this development. Even though the OP’s LPA has not introduced a CIL charging scheme, where does their post mention works have commenced? Link to comment Share on other sites More sharing options...
Alan Ambrose Posted May 6 Share Posted May 6 Well the OP says that he wants to call a start to preserve the permission for posterity. I’m pointing out that a couple of BH members have fallen foul of an expensive CIL gotcha. I only didn’t make this mistake (about £60K cost to me) as I’ve taken to running everything past my LPA’s CIL people before making any move pre-permission. Link to comment Share on other sites More sharing options...
kandgmitchell Posted May 7 Share Posted May 7 You will need to clear all the pre-commencement conditions before a start could be defined as commencing the works. Link to comment Share on other sites More sharing options...
twice round the block Posted May 7 Share Posted May 7 On 05/05/2024 at 23:10, DevilDamo said: @twice round the block Apart from the OP is asking about Planning, not Building Regulations. @DevilDamo To preserve planning. I did read it correctly and my response was regarding keeping ours live for another 3 years. Nothing to do with building regs. Link to comment Share on other sites More sharing options...
Temp Posted May 7 Share Posted May 7 You will need to ask the planners what constitutes starting development. Normally they expect you to have dug foundations and had them inspected by the BCO but I suspect this is so they have some record of work having been done. Planning law doesn't require that, it just say development must have started. The definition of what counts as development is open to interpretation. It's quite possible the planners won't tell you what you need to do or give you any confirmation that you have done it. Officially the only way is to do something and apply for a certificate of lawfulness/development on the grounds that work has started. I've seen this done for a wind farm they don't want to build yet. They build a short length of an access road and apply for a certificate. 1 Link to comment Share on other sites More sharing options...
ToughButterCup Posted May 7 Share Posted May 7 On 05/05/2024 at 20:00, Norbert said: ... Do we need to get our plans agreed with Building Control before we we start on [...]? Do they then need to inspect the installation and sign that off as proof of anything? ... You have full PP? Or Outline permission? Have you submitted your plans to BC for approval? (Often called The Building Regs Application) If so ( and they are happy) , then No is the answer. No (as proof) is the answer to the second question too. One quick way I have heard of as showing commencement is to install a temporary electricity supply (you may already have one?). Photograph and date the installation. Send via email to Building Control. Job jobbed. As usual @Temp (above) has the definitive, official, water-tight answer. It's a bore though. And costs munee. 1 Link to comment Share on other sites More sharing options...
DevilDamo Posted May 7 Share Posted May 7 3 hours ago, twice round the block said: @DevilDamo To preserve planning. I did read it correctly and my response was regarding keeping ours live for another 3 years. Nothing to do with building regs. So why did you speak to Building Control? 🤔 Link to comment Share on other sites More sharing options...
twice round the block Posted May 11 Share Posted May 11 On 07/05/2024 at 19:14, DevilDamo said: So why did you speak to Building Control? 🤔 Sorry planning, wrong department. Too many builds on the go, at once, hence the need to keep a PP alive for another 3 years. Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now