I received the estimators online quote back today, and I was quite surprised by the labour cost for the slab.  Just going through the numbers to see where I could potentially save some money.  12k in labour sounds rather expensive.

 

Ground floor
UoM
Labour
Quantity
Labour
Total £
UoM
Material
Quantity
Material
Total £
Lay & compact MOT type 1 hardcore, delivered loose.
Tn
43.148
2,021.23
Tn
44.000
1,409.86
Tool hire, plate compactor for the above task.
>
>
>
Dy
1.000
36.63
Sand blinding, delivered loose.
Tn
14.383
524.03
Tn
15.000
481.13
Foil faced rigid PIR insulation board 2400x1200x100mm.
M²
159.807
1,176.33
Ea
59.000
3,122.47
Polythene membrane, blue standard duty 300mu 100m2 rolls.
M²
159.807
665.42
Rl
2.000
128.74
Polythene vapour control layer, blue standard duty.
M²
159.807
998.13
Rl
2.000
128.74
Floor slab, cold bridge 200mm upstand
M¹
143.100
554.40
Ea
11.000
222.18
Concrete floor slab 100mm thick.
M²
159.807
2,994.40
M³
16.000
2,377.58
Tool hire, petrol power float for the above task.
>
>
>
Dy
1.000
45.79
Floor Screed, premixed delivered 1:3 mix.
M²
154.038
3,347.12
Tn
24.000
3,228.49
       
12,281.06
   
11,181.61

 

This is the first time I've used estimators online, and I think I could have maybe been more specific.  The floor plan had a kitchen with island shown, but they haven't put a kitchen in the quote or the utility room.

 

 

 

  • 2 weeks later...
Posted

I found their labour and material pricing very hit and miss. But it does give a great starting point and you also have a nice list of the activities to help with actual quotes.

 

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...