Jump to content

Recommended Posts

Posted

 I had this from building control. What do I need to comply ? Does the cabling need to be connected to any sort of termination point ready for a charger to be added at a later date ?if so what do I need. 
 

‘The requirement is one charging point for each unit, plus cabling to be provided per associated vehicle space within the boundary of the properties.’

Posted

I read that as you must provide 1 working charge point, PLUS the cabling installed ready to add additional charging points for each vehicle space you have so those can be upgraded later.

 

for the additional ones, I would just say suitable SWA cable with the ends sealed to keep water out, from the parking space to the consumer unit, ready to be terminated when you want them.

  • Like 1
Posted

Ok thanks. One of the three parking spaces is counted as the garage so would I have a charger point set up inside the garage ? Then I could provide cabling to the pillars each side of the garage doors for future chargers ?

Posted (edited)

Data cable too probably unless the unit works off 4G

 

personally I would fit ducts to proposed positions, pull in cable such as EV ultra, or separate Swa/ data.

 

Edited by TonyT
  • Like 1

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...