 I had this from building control. What do I need to comply ? Does the cabling need to be connected to any sort of termination point ready for a charger to be added at a later date ?if so what do I need. 
 

‘The requirement is one charging point for each unit, plus cabling to be provided per associated vehicle space within the boundary of the properties.’

Link to comment
Share on other sites

I read that as you must provide 1 working charge point, PLUS the cabling installed ready to add additional charging points for each vehicle space you have so those can be upgraded later.

 

for the additional ones, I would just say suitable SWA cable with the ends sealed to keep water out, from the parking space to the consumer unit, ready to be terminated when you want them.

  • Like 1
Link to comment
Share on other sites

Ok thanks. One of the three parking spaces is counted as the garage so would I have a charger point set up inside the garage ? Then I could provide cabling to the pillars each side of the garage doors for future chargers ?

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...