Hi folks. Anyone understand how you install a radon barrier, when you have block and beam ground floor - the builders QS says we need to "fill" up the underside on the floor. Is this correct - I would have thought it can be installed lower down. Approx, the void w/o fill would be 900mm. TIA

Edited by Jimbo37
tags
Link to comment
Share on other sites

No. Check out the Visqueen detail. The DPM/radon barrier are above the slab with all joints to DPCs overlapped and taped. FYI don't fill up to the underside of block and beam floor. The reinforcement doesn't have enough cover. Example below.

 

Contact Visqueen and they will do you a site specific detail for your build.

 

 

 

image.png.5be38ec9d7c20922270288aeab51f810.png

  • Like 1
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...