Moonshine Posted September 7, 2022 Posted September 7, 2022 The screed is in and has had about 3 weeks setting. I want to layout my non structural studwork on the screed but dont want to screw into it as there is UFH pipes in it. What can i use to stick the dpc onto the screed, then what to use to stick the sole plate to the dpc?
markc Posted September 7, 2022 Posted September 7, 2022 (edited) Assuming your floor finish will be tiles or wood then very little lateral load on an internal wall as the floor finish will hold it in place. Good ole Ct1/OB1 etc will do nicely. and as the sole plate is above screed and UFH etc then no real need for DPC Edited September 7, 2022 by markc
JohnMo Posted September 7, 2022 Posted September 7, 2022 Daft question, why would the UFH pipes be anywhere near where the walls are going to be?
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now