New Electrical Supply


Kelvin

Recommended Posts

Hi all

 

I have installed a kiosk and SSEN have installed electricity supply and fuse. Octopus (via SMS) are coming on the 20/9 to install the meter. I’ll then arrange for an electrician to come out and install a mini CU, some site power sockets, earth road, and switched fuse ready for the SWA to the house. I plan to keep the meter here permanently. 

 

I’ve spoken with the SMS about what else they need done before they arrive and they’ve said what I have is fine but they were a little vague. However, I was chatting to another self-builder today and he said they won’t install the meter unless I have an earth rod so I’m a bit confused.  I could just get ah electrician to do all of the above ahead of the meter install anyway. Any advice?

4CD34A5A-D177-4CCB-A5DD-8876B6448685.jpeg

3F7DDFAF-B01F-40D9-9603-C1427ABE2593.jpeg

Link to comment
Share on other sites

That’s what I originally thought but when I spoke with SMS several weeks ago they said what I have is fine. I even sent them a picture. I’ll get an electrician round to do their side of it regardless of what SMS have been telling me. 

Link to comment
Share on other sites

  • 1 month later...

Meter installed. He said they prefer to install the meter with nothing else in the cabinet other than the fuse because more often than not the electrician doesn’t leave enough room for the meter and master switch. So it would have been with the other electrical work. 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...