connick159 Posted November 1, 2020 Share Posted November 1, 2020 (edited) Hi, walls are all done, roof on, windows all fitted and I've just realised the brickies didn't carry the cavity wall insulation (PIR board) 150mm below the DPC. Stressing out a bit as too late to change it but about to put down floor insulation in prep for UFH and screed. I'll be putting perimeter insulation before the screed but very concerned about cold bridging now. Are there any options for blown insulation into the bottom of the cavity? I still have access in spots where door and window cils not yet installed. Am I worried over nothing or is this a big oversight and will leak heat unless resolved? Thanks. Edited November 1, 2020 by connick159 Link to comment Share on other sites More sharing options...
Oz07 Posted November 1, 2020 Share Posted November 1, 2020 I would think blown beads is am option drilled from outside. Look into it 1 Link to comment Share on other sites More sharing options...
Iceverge Posted November 1, 2020 Share Posted November 1, 2020 +1 We intentionally build and insulated the cavity for 500mm below dpc with bonded bead to mitigate bridging. Link to comment Share on other sites More sharing options...
connick159 Posted November 1, 2020 Author Share Posted November 1, 2020 1 hour ago, Iceverge said: +1 We intentionally build and insulated the cavity for 500mm below dpc with bonded bead to mitigate bridging. Thanks for the updates, what company did you use for the beads? Link to comment Share on other sites More sharing options...
Iceverge Posted November 2, 2020 Share Posted November 2, 2020 Local contractor in Ireland affiliated to Energystore Belfast. Don't think they cover Britain. 1 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now