The next day. Our slab was poured on a Friday, ICF started on the Monday, and poured 2 weeks after slab. You don't need concrete to get to full 28 day strength unless you are putting a lot of force against it, eg. Backfilling or concrete slabs.

Edited by Conor
  • Like 1
Link to comment
Share on other sites

16 minutes ago, hallega said:

Hi Conor, it's a basement...so l suppose 28 days then.....he's going to be spitting feathers!!! Thanks for the reply.

Morning, you only need to wait to back fill the basement, you can get on with the ICF walls withing a few days of the pour.

  • Like 2
Link to comment
Share on other sites

1 hour ago, hallega said:

Hi everyone, 

 

Do we have to wait for 28 days before we can start placing out our Durisol blocks, hubby is chomping at the bit, anyone advise anthing else?

3 days is how long you should wait if you are going by a civils/structural guide.

 

 

  • Like 1
Link to comment
Share on other sites

1 hour ago, hallega said:

Hi Conor, it's a basement...so l suppose 28 days then.....he's going to be spitting feathers!!! Thanks for the reply.

 

Only 28 days for Backfilling. ICF can start straight away.

 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...