MarkH Posted December 23, 2016 Share Posted December 23, 2016 The main bit of our house is just under 11m long and therefore the purlins (200x100mm green oak) aren't going to be single lengths as 11m+ oak isn't easy to come by. So given I'll be using a couple of lengths where should I scarf them together? Close to one of the four trusses? In the middle? Link to comment Share on other sites More sharing options...
Stones Posted December 23, 2016 Share Posted December 23, 2016 One for your SE to specify I think? Link to comment Share on other sites More sharing options...
MarkH Posted December 23, 2016 Author Share Posted December 23, 2016 I've emailed him, just thought I'd ask here anyway - just making eye-contact with the SE costs £65... His drawings only mentioned the purlin size, not the location of any joints. 1 Link to comment Share on other sites More sharing options...
PeterW Posted December 23, 2016 Share Posted December 23, 2016 41 minutes ago, MarkH said: The main bit of our house is just under 11m long and therefore the purlins (200x100mm green oak) aren't going to be single lengths as 11m+ oak isn't easy to come by. So given I'll be using a couple of lengths where should I scarf them together? Close to one of the four trusses? In the middle? It will have to be over a truss but the SE would need to specify the joint scarf / method if it is structural join. From experience though, they tend to be over spec anyway so you may find they just need to be of equal length if the truss is taking the load. Link to comment Share on other sites More sharing options...
Nickfromwales Posted December 27, 2016 Share Posted December 27, 2016 On 23/12/2016 at 11:19, MarkH said: His drawings only mentioned the purlin size, not the location of any joints. Strange that he didn't identify the issue and provide a mitigation strategy in his return . He'd have known all about how far that timber could traverse before needing a joint so maybe next time you get charged for eye contact, bring that up . Link to comment Share on other sites More sharing options...
MarkH Posted September 14, 2017 Author Share Posted September 14, 2017 Lap joints currently in construction. The purlins are joined at the trusses, both are notched for longitudinal restraint. 24 lap joints... I'm six in and already cut myself twice and dropped a beam on my toe. 1 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now