Frame progress


jamieled

1804 views

The last week or so we've been blessed with pretty nice weather which has allowed for good progress on the frame. We hired in a hiab lorry for a morning to help with lifting the gables, ridge beam and roofing.

20190917_111448.thumb.jpg.00c542390cce9f2503ab465572ecf78f.jpg

 

As everyone probably finds out, now we start to get a better sense of the size of the house and how it sits in the landscape.

20190919_144347.thumb.jpg.bc6a475291ba12bcaddae744841f9951.jpg

 

SSE came in the other day for our grid connection. Those who have been following our progress might remember this was quite pricey, and when you see the number of vehicles involved you start to understand why.

20190920_090004.thumb.jpg.1f7331643db43ef7bbab90f4cbfc1251.jpg

 

Here's hoping for a few days of decent weather to allow us to complete the roof.

  • Like 3

3 Comments


Recommended Comments

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...