Week 4 The R-Wall ICF arrives on site
The last bit of soil pipe and inspection chambers that are close to the house are completed.
The ICF is delivered and by the end of the week we have the start of door and window openings.
The insulation is extruded polystyrene XPS 100mm each side of the concrete cavity. U value of 0.14
The windows have rebar in them before 50mm insulation closures are added.
At the weekend we had a yellow wind warning for the South West, our home weather station recorded top gusts of 40mph. I’m pleased to say the R-wall ICF survived with no problems.
Total man days of labour week 4 is 22 man days split between Groundworks and ICF builders.
The build is going on very close to our workshop entrance which makes the delivery of vehicles and test drives limited. This week we took delivery of a previous customers Jensen CV-8 which now has a new owner who has sent it to us for further works over winter.
- 3
7 Comments
Recommended Comments
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now