Jump to content
  • entries
    6
  • comments
    19
  • views
    3252

About this blog

Demolishing an 1970's tin and wood cow shed and building a ICF bungalow for me, my husband and our Greyhound.

Entries in this blog

Week 4 The R-Wall ICF arrives on site

The last bit of soil pipe and inspection chambers that are close to the house are completed.   The ICF is delivered and by the end of the week we have the start of door and window openings. The insulation is extruded polystyrene XPS 100mm each side of the concrete cavity. U value of  0.14   The windows have rebar in them before 50mm insulation closures are added.   At the weekend we had a yellow wind warning for the South West, our home weather station recorded

Susie

Susie in General

Week 3 The slab

Another beautiful week in Cornwall only 7mm of rain on the Sunday The week starts with laying the soil pipes then it was sand, hardcore, burying the soil pipes, laying the radon barrier, mesh and more concrete for the slab leaving a lovely surface to start the ICF walls next week.  And the field was cut and baled, not as much as a normal September cut due to us moving our spoil down to the far field and tramping the grass down and making a very very muddy gateway between our two fields

Susie

Susie in General

Week 2 Trench foundations and starter blocks

Despite the yellow weather warning we luckily had the coastal wind pushing it away, most of it fell on Tuesday but only 6mm The trench foundations are excavated and inspected. Then the concrete poured, and the first blocks laid followed by dolly blocks and internal supporting wall starter blocks Total man days of labour for week 2 is 13

Susie

Susie in General

Week one clearing the site

We have finally started to build.  Day 1 was Monday 2nd September 2024.  It was nearly 3 years from the first invoice which was for the private planning consultant to discuss and review the possibility of demolishing one of our old barns and building a bungalow on its footprint.  Back then we weren’t overly confident of our chances but the consultant gave us a fairly good chance. Our current home is a listed property on 3 floors. It is far too big for us with 4 double beds, 3 bath

Susie

Susie in General

Building Regs, Part O and SAP

My previous blog entry ended at submitting the building regs in March, although they were not validated until 5th April and then refused on the 31st May.  I believe my architect had complained on them taking too long so I am guessing when they found he had not included a turning circle for a fire engine they refused them as giving the architect extra time would have hit their own time targets.   We resubmitted 1st June and finally had approval on the 5th July.  A few conditions but nothing unexp

Susie

Susie in General

From the start of planning to site electric

We moved from Manchester to Cornwall 6 years ago and we are very happy with the overall location.  Our existing converted barn, was converted by the previous owner and is very nice but is built on three levels and has 4 double beds, kitchen, dinner, lounge and snug and 3 baths so it is far too big for us when we retire.  When we bought the house I always say we chose it for the working barn apx 300m2, not the barn we live in.  We are building for our future in the hope that we can continue to li

Susie

Susie in General

×
×
  • Create New...