Week 2 Trench foundations and starter blocks
Despite the yellow weather warning we luckily had the coastal wind pushing it away, most of it fell on Tuesday but only 6mm
The trench foundations are excavated and inspected.
Then the concrete poured, and the first blocks laid followed by dolly blocks and internal supporting wall starter blocks
Total man days of labour for week 2 is 13