After obtaining planning, i got my building controll aplication under way. I had 2 options
- Pay £1100 for Building Notice
- Pay £900 for Full Plans.
Everyone on here recommends full plans, and it was a cheaper fee. I knew i'd have to either pay for the plans or do them myself. I opted to do them myself after loads of research on this forum (particiularily inspired by @HerbJ )
Here's my version of Herb's spec.
Building Regulation Specification Redac
I used the knowledge of this forum to help me work out what i wanted to build. I was told repeatedly to knock down and re-build, and i kinda wish i'd of gone down that route now, but i decided to stick with what i had and make it work. With that said, i'm not paying much VAT, i'm doing a lot of the work myself, and the trades i do employ aren't VAT registered anyway. The 0% VAT incentive of going new build wouldn't have been quite as much as a game changer as i thought it might be.
I