janelondon Posted August 24, 2018 Share Posted August 24, 2018 Hello, Can anyone share the rough percentage costs of a TF build over the various build stages, perhaps measured against the typical drawdown stages of a self-build mortgage? So e.g. - foundations X%, frame erected X%, watertight X% and so on? Bonus if you can share timeframes taken to get to each stage - I know this will vary widely depending on size/scale/how build is managed etc. but would like to get a bird's eye view of different experiences. (Trying to plan out cashflow requirements) Thank you! Link to comment Share on other sites More sharing options...
Jeremy Harris Posted August 24, 2018 Share Posted August 24, 2018 Our initial ground works were very complex and untypical (900 tonnes of soil removed, big retaining wall built, borehole drilled for water, etc) so I'd ignore the basic ground works time below. The rest are just the best I can remember, really. Ground works, to level plot with water, drainage and electricity supplies in, but no house foundations = 5 months (should have been 7 weeks - things went horribly wrong with the borehole drilling). Foundations = 4 days, including installing the UFH pipes in the slab. Timber frame erection to weathertight, but with door and window opening sheeted over and roof membrane and battens on, but no slates = 4 1/2 days Door and window installation = 1 day (a bit less than this, but they came back for an hour on another day to fit one incorrectly supplied window). At this stage the house was secure and watertight Installation of frame inner VCL board and filling walls and roof with blown insulation = 5 days Installation of in-roof solar panel frames and wiring = 2 days Installation of roofing slates, barge boards, soffits, fascias, guttering and downpipes = 5 days Installation, wiring and testing of in-roof solar panels and inverter = 2 days External cladding of frame = 7 days First fix plumbing, wiring and ventilation system = 4 weeks (largely me on my own - could have been a lot quicker!) Plaster boarding and skimming all internal walls = 2 weeks (with me installing acoustic insulation as the guys were boarding out) Internal wall and ceiling decorating = 6 days, one chap working on his own, just emulsion on all walls and ceilings Second fix electrics and testing = 1 week Internal joinery = 8 weeks (8 days for joiner to fit frames and internal doors, the rest me working on my own fitting skirting and architrave, all oak, so took longer). Travertine flooring on ground floor and in bathrooms = 3 days (local tiler, working with one labourer) Bamboo flooring = 5 weeks (me working on my own, should have been a LOT quicker) Kitchen installation = 3 weeks, two weeks me working on my own fitting kitchen units (should have been about two days) 1 week delay for the stone masons to template then come back and fit the stone work tops. At this point I really stopped keeping track of time -things really started to drag out as I was largely working on my own. Sorry I can't put costs against these elements right now, but I may have a go later. Link to comment Share on other sites More sharing options...
Ferdinand Posted August 24, 2018 Share Posted August 24, 2018 39 minutes ago, janelondon said: Hello, Can anyone share the rough percentage costs of a TF build over the various build stages, perhaps measured against the typical drawdown stages of a self-build mortgage? So e.g. - foundations X%, frame erected X%, watertight X% and so on? Bonus if you can share timeframes taken to get to each stage - I know this will vary widely depending on size/scale/how build is managed etc. but would like to get a bird's eye view of different experiences. (Trying to plan out cashflow requirements) Thank you! various people have detailed breakdowns on their blogs, but you will have to look. I can give you one ? Finishing : everything left + available card balances + 10%. F 1 Link to comment Share on other sites More sharing options...
janelondon Posted August 24, 2018 Author Share Posted August 24, 2018 Thank you so much @JSHarris ! That was INCREDIBLY helpful. And @Ferdinand - that sounds about right haha! Link to comment Share on other sites More sharing options...
newhome Posted August 24, 2018 Share Posted August 24, 2018 There is this post that might be useful 1 Link to comment Share on other sites More sharing options...
Jeremy Harris Posted August 24, 2018 Share Posted August 24, 2018 Just been digging out costs. I just remembered that I'd put together a simplified spreadsheet detailing our costs, which covers most things. It may need some work to relate the costs in it to the times above, I'm afraid. Simplified costings - 230421014.pdf 1 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now