Weebles Posted July 8, 2018 Share Posted July 8, 2018 Just about to start fitting UFH pipes onto the steel mesh in our MBC slab. Designer has used 150mm centres for the pipes. Guys on site say that 200mm centres are sufficient. I have ordered enough pipe for 150mm centres so there are no cost savings to be made now. It will be a gas boiler supplying the hot water for the UFH. Any views? Link to comment Share on other sites More sharing options...
Nickfromwales Posted July 8, 2018 Share Posted July 8, 2018 It'll be of no real detriment at 150mm centres but it would probably mean more loops and a bigger manifold eg more expense. Pennies in the grand scheme TBH. Link to comment Share on other sites More sharing options...