Wednesday at 20:181 day It's time to tank.But I only have a small section to do sealing the joins here. There's no harm in just tanking over the entire of this is there, may as well use up the solution otherwise it would just go in the bin?
Wednesday at 21:141 day As an aside, with my tanking kit the instructions said first coat vertical, second horizontal, third vertical. As in brush / roller lines vertical on the 3rd coat for water to run down. Belt 'n braces.
Wednesday at 22:261 day Author Makes sense I suppose. I haven't opened my tanking kit but I'll remember this for when I get to the job and do just that.
Wednesday at 23:061 day 1 hour ago, Onoff said:As an aside, with my tanking kit the instructions said first coat vertical, second horizontal, third vertical. As in brush / roller lines vertical on the 3rd coat for water to run down. Belt 'n braces.Ffs. Water will not defy gravity because the direction of the brush stroke define these laws.“Springers final thoughts……”Water cannot run down these ‘lines’ as they will be smothered in feckin tile adhesive.End transmission. 🤦♂️😌
Wednesday at 23:231 day 3 minutes ago, Mr Punter said:I like the extract vent.These are the way forward. “Repent, all yea heathen, utilitarian ruffians, and accept’th not the petrol station toilet type units provided by the cheap-seat-lovers”.Do not spend 7 figures making your dream home, and fit anything less.
Yesterday at 00:081 day Author 50 minutes ago, Mr Punter said:I like the extract vent.Canny bit of graft went into that vent.
17 hours ago17 hr 6 hours ago, Super_Paulie said:Canny bit of graft went into that vent.Can they be fitted vertically on a wall?Just thinking about tanking and shower trays and first fix on first floor. If you want the tanking done before the tray goes in you have to board the wall first. But if you want to put the tray in after the tanking then you need to connect the waste up afterwards. So you need to leave GF ceiling boards off to finish waste plumbing?
16 hours ago16 hr 49 minutes ago, Oz07 said:Can they be fitted vertically on a wall?Just thinking about tanking and shower trays and first fix on first floor. If you want the tanking done before the tray goes in you have to board the wall first. But if you want to put the tray in after the tanking then you need to connect the waste up afterwards. So you need to leave GF ceiling boards off to finish waste plumbing?If the wall is made a bit thicker yes, but you’d need to jerry rig the rear connector to turn 90° immediately off the rear of the vent, with something like this. Then convert back to generic duct with the same fitting (a straight one is available if needed) and then go 125 > 92mm in an Ubbink type fitting.
11 hours ago11 hr All the shower tray fitment can be done from ‘above’. You dry fit the waste and lay the tray down, to check it all aligns and the rubber seal of the waste is just barely touching the underside of the tray. This needs to allow for the thickness of whatever you are going to bond the tray down with.Then glue the waste pipework, preserving the exact position. This needs movement, so it can be pulled up and maybe move 5mm either way off centre for wiggle room. You then CT1 the wall > tray contact areas, plus both under and over the rubber seal, set your adhesive, and get it down.This assumes the wall is already tanked down to the floor, and the CT1 is going against that.Then you screw the shower drain into the trap which pulls the trap body upwards and clamps that to the underside. Look into it to see if any needs wiping out, and clean as necessary.Immediately send a couple of hundred litres of water down it so it can be lifted if it leaks. Don’t wait for the CT1 to cure, it’s water tight / impervious immediately.
11 hours ago11 hr A lot of plumbers want to fit the tray at first fix. I wouldn't really want to tell one how to suck eggs. Maybe you could board the shower area 6" off the floor, tank, fit the tray to this at first fix then board rest of wall and tank over. Not ideal but not as bad as tanking after the tray is fitted.
11 hours ago11 hr Author im personally going to tank down to the deck, then get my tray in. I can still access the trap from above to check for leaks but i have it all ready to go and welded in place already as in an earlier photo below.
11 hours ago11 hr 14 hours ago, Nickfromwales said:Ffs. Water will not defy gravity because the direction of the brush stroke define these laws.I think this is about ensuring proper application. If you just go vertical your brush might bridge over a horizontal crack, that would definitely be filled if you brush horizontally.Like most things, the instructions are designed for idiots / to deflect responsibility if the product fails. For any competent person its irrelevant.
5 hours ago5 hr 5 hours ago, Ed_ said:Like most things, the instructions are designed for idiotsWorked for me...
2 hours ago2 hr It’s pretty simple to see that it’s covering well, just don’t be a tight-arse when applying it.
Just now1 min 2 hours ago, Nickfromwales said:It’s pretty simple to see that it’s covering well, just don’t be a tight-arse when applying it.Well my waterproofing was impossible to apply at the stated coverage, and I tried!I'm convinced they put an unachievable figure deliberately so they always have a get out.