AdaminCymru Posted Sunday at 19:55 Posted Sunday at 19:55 Please could I have a sense check. Is this acceptable method of constructing steps within a retaining wall? The wall was existing, and steps new and part of the patio project. Clay soil behind the retaining wall, dug out on a slope. Mortar / concrete laid straight onto clay soil and steps formed off this. Brick face and porcelain slab on the top. Thank you
Mr Punter Posted yesterday at 11:20 Posted yesterday at 11:20 Looks OK to me. I would rather a load of mass concrete and some tile adhesive rather than a mortar bed as the clay may shrink and heave which could loosen the tiles, but it is built now. Maybe keep a few tiles in the garage in case? Some drainage through the wall would be good.
Conor Posted 12 hours ago Posted 12 hours ago Pretty much how we did our ramp/steps, well compacted ground, a good thick mortar bed. Down a year an dno sign of movement. BUT... make sure there is drainage out through the side walls or else any water will make its way up through the pavers.
AdaminCymru Posted 20 minutes ago Author Posted 20 minutes ago @Conor @Mr Punter. Thank you both for your comments
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now