Jimbouk Posted October 29, 2017 Share Posted October 29, 2017 Main contractor almost finished their work, second fix down to me. Before I settle their account, minus 6 month retention, what should I check with regard to building regs? Thanks James Link to comment Share on other sites More sharing options...
ProDave Posted October 29, 2017 Share Posted October 29, 2017 Get your building control inspector for a walk around to check he is happy with everything as built to date. That's what I did before paying the final stage payment. Link to comment Share on other sites More sharing options...