CalvinHobbes Posted July 28 Share Posted July 28 So plasterboard on, plasterer should be here hopefully in a week max but wondering, when should I leave over a wall mounted sink with two drawers underneath for the upstairs bathroom? Link to comment Share on other sites More sharing options...
Kelvin Posted July 28 Share Posted July 28 (edited) Check what the lead time really is. If you have space get them on-site now. I had all the bathroom stuff on-site early to allow me to set the pipes, check fittings, sizes etc Also read the instructions. I stupidly fitted the sink first then offered the cabinet up to the sink. Should have been the other way around. 🙄 Edited July 28 by Kelvin Link to comment Share on other sites More sharing options...