CalvinHobbes Posted May 2 Share Posted May 2 Hiya, how many commando sockets can you put in a temporary supply (single phase 16v) to obey building regs? Link to comment Share on other sites More sharing options...
Conor Posted May 2 Share Posted May 2 Two. It's NIE requirement. We just fitted another two after all the connection works done and meter installed. Link to comment Share on other sites More sharing options...
CalvinHobbes Posted May 2 Author Share Posted May 2 1 hour ago, Conor said: Two. It's NIE requirement. We just fitted another two after all the connection works done and meter installed. So you fail the meter guy if you fit 1? Link to comment Share on other sites More sharing options...
Conor Posted May 2 Share Posted May 2 3 hours ago, CalvinHobbes said: So you fail the meter guy if you fit 1? No, one is fine. Can't have more than two. 1 Link to comment Share on other sites More sharing options...
CalvinHobbes Posted May 3 Author Share Posted May 3 Much obliged Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now