Skip to content
View in the app

A better way to browse. Learn more.

BuildHub.org.uk

A full-screen app on your home screen with push notifications, badges and more.

To install this app on iOS and iPadOS
  1. Tap the Share icon in Safari
  2. Scroll the menu and tap Add to Home Screen.
  3. Tap Add in the top-right corner.
To install this app on Android
  1. Tap the 3-dot menu (⋮) in the top-right corner of the browser.
  2. Tap Add to Home screen or Install app.
  3. Confirm by tapping Install.

Minimising floor build-up with UFH

Featured Replies

Hi all,

 

The spec for our ground floor (with UFH) is:

 

  • Type 1
  • sand blinding
  • DPM
  • 150mm slab
  • 150mm PIR with pipes clipped on
  • 75mm screed

 

Our ceiling heights downstairs are on the lower side at 2.15m so anything we can gain on the floor would be an advantage. Before I approach Building Control and open that can of worms, is there any reason we couldn't do:

 

  • Type 1
  • sand blinding
  • DPM
  • 150mm PIR
  • DPM with pipes clipped down into it
  • 150mm slab

 

Apart from having to make sure we get a good, level finish on the slab, it'd save us 75mm, plus the additional cost of screed. I also understand the UFH would be a bit slower to heat up but wouldn't it then retain temperature for longer?

 

Welcome any thoughts.

 

13 hours ago, Ben Weston said:

Hi all,

 

The spec for our ground floor (with UFH) is:

 

  • Type 1
  • sand blinding
  • DPM
  • 150mm slab
  • 150mm PIR with pipes clipped on
  • 75mm screed

 

Our ceiling heights downstairs are on the lower side at 2.15m so anything we can gain on the floor would be an advantage. Before I approach Building Control and open that can of worms, is there any reason we couldn't do:

 

  • Type 1
  • sand blinding
  • DPM
  • 150mm PIR
  • DPM with pipes clipped down into it
  • 150mm slab

 

Apart from having to make sure we get a good, level finish on the slab, it'd save us 75mm, plus the additional cost of screed. I also understand the UFH would be a bit slower to heat up but wouldn't it then retain temperature for longer?

 

Welcome any thoughts.

 

Hi.

You can lose at least 30mm of concrete (assuming a steel reinforcing mesh will be utilised) but the PIR is on the limit. How much thickness have you allowed for type 1 and sand?

  • Author

The 150mm slab was specced for mesh already so don't know if we can reduce that but I can ask the question. Not intending to lower PIR, I'd actually have more if we could as we're over-specced everywhere else.

 

Any reason my suggestion wouldn't work?

On 12/06/2023 at 09:52, Ben Weston said:

Hi all,

 

The spec for our ground floor (with UFH) is:

 

  • Type 1
  • sand blinding
  • DPM
  • 150mm slab
  • 150mm PIR with pipes clipped on
  • 75mm screed

 

Our ceiling heights downstairs are on the lower side at 2.15m so anything we can gain on the floor would be an advantage. Before I approach Building Control and open that can of worms, is there any reason we couldn't do:

 

  • Type 1
  • sand blinding
  • DPM
  • 150mm PIR
  • DPM with pipes clipped down into it
  • 150mm slab

 

Apart from having to make sure we get a good, level finish on the slab, it'd save us 75mm, plus the additional cost of screed. I also understand the UFH would be a bit slower to heat up but wouldn't it then retain temperature for longer?

 

Welcome any thoughts.

 

I’d use option 2 

The only thing I did different was instead of 150mm concrete with rebar mesh, I used 100mm fibre reinforced concrete, much cheaper and easier than laying rebar mesh. 
Plus it works better with UFH as the aggregate max is 10mm so it’s more like a screed than concrete and is poured very wet so is self compacting 

the slab wont be level enough to lay flooring on.

 

Dig it down more and the problem is solved.

  • Author
9 minutes ago, Dave Jones said:

the slab wont be level enough to lay flooring on.

 

Dig it down more and the problem is solved.

 

Can't dig down any more as the original house is only three bricks deep and not on foundations - we're as low as we can go unfortunately. Surely if it's powerfloated, it'll be level enough?

 

3 hours ago, Chanmenie said:

I’d use option 2 

The only thing I did different was instead of 150mm concrete with rebar mesh, I used 100mm fibre reinforced concrete, much cheaper and easier than laying rebar mesh. 
Plus it works better with UFH as the aggregate max is 10mm so it’s more like a screed than concrete and is poured very wet so is self compacting 

 

Interesting. I've had several people suggest fibre reinforced concrete rather than meshing. Seems easier, cheaper and quicker; surely there's a reason to mesh over fibre though?!

Create an account or sign in to comment

Account

Navigation

Search

Search

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.