Hi

From top of trench block to floor level is 225mm insulation will hit top of trench block.  Does anyone put weep vents just above ground level incase cavity gets filled with water.  Cannot find  anything on NHBC site about this?

cheers

Posted

I haven’t in either of our builds 

Some companies and most housing associations do

Its quote Simple to do You run a tray all the way around the perimeter sloping down to dpc 

Some do the same at chamber also 

Usually local authority 

 

Posted

 might put a few at 150mm from floor level so during build water can just drain out.  I've  not this done in the past like you  and there's no tray required for radon etc.

Posted

if you need to 'move' your DPC level up to accommodate for level threshold for example then a tray 1 block up from DPC (with weeps at youf FFL) will allow you to breach the normal 150mm that has to be maintained below FFL.  Just make sure the brickie adds a second 4" dpc 1 block up on the outer brickwork as well.

 

Costs peanuts to do and gives really good flexibility for patio's, sloping approaches etc

 

 

  • Like 1

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...