Jump to content

Recommended Posts

Posted

I realise I don’t have long to wait for an answer to this question, but I’m looking for a little reassurance (if appropriate)!

 

We are having our conservatory replaced and we are running to a VERY tight schedule because we have a kitchen being delivered on the 5th December and the only place it can go is in the new conservatory.

 

The brick walls and windows are done and the roof is almost complete. It was meant to be completed today and the electrician coming tomorrow for first fix (plug sockets and spit lights).
 

However, there is still one window pane to put in the roof so there’s effectively a gaping hole in it for rain to get in. Tomorrow the roofers are coming in to finish the roof.

The concrete floor, because of the weather and because we only have a partially constructed roof, has half an inch of rain water on it, having been exposed to the elements for a week.

Do you think the electrician can still come and do his work with it being that wet on the floor? If he can’t, how can it be dried??

 

thanks

 

 

Posted
  On 27/11/2022 at 21:25, ProDave said:

First fix yes, advise him to bring wellies and a raincoat for if the roofers don't get finished.

Expand  


Thank you. Are you being serious that it should still be ok to do? To be honest, I don’t really know what first fix even means! 

Posted

First fix is installing the cables ready for plastering the walls etc.  I certainly would do that in wet.  I would not do final fix, connecting it all and testing it until the building is dry.

  • Thanks 1

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...