Jump to content

Recommended Posts

Posted

Hi there 

I’m just after some advice I’m building my own single story extension myself 3m x 4m

foundations have been dug and passed by building control. When we came  to concrete 3/4 of the pour was done as one but was late in the day we couldnt quite finish the pour, so about 1.5 metre section was poured the following morning and just butted up to previous pour. Is this likely to cause structural problems down the line 

thanks 

Posted

Best to check with your BCO, but I'd have thought you'd need to drill and rebar into the set section before pouring the rest. 

Posted

Shouldn’t have been poured with a vertical join unless it’s got rebar or steel dowels in the join. In reality it “shouldn’t” move but I would be putting a couple of 215x140 1200mm concrete lintels over the joints and building off those - and hoping BCO doesn’t notice !

Posted

Thanks for the replies, unfortunately the brickwork is nearly up and it’s only just dawn on me that this can be a problem,

what’s the worst case scenario going forward? 

Posted
14 minutes ago, Jimbo1976 said:

Thanks for the replies, unfortunately the brickwork is nearly up and it’s only just dawn on me that this can be a problem,

what’s the worst case scenario going forward? 

 

Differential movement and you start seeing cracks

  • 2 weeks later...
Posted

If the ground is good and the foundations were put in at the correct depth then I wouldn't worry.

 

If there are issues in future you could crack stitch the masonry to give it more continuity strength. 

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...