Mr Blobby Posted May 30, 2022 Posted May 30, 2022 Is there a curing time for KORE insulated slab before laying masonry blocks on it? How long, roughly, should I insert into the plan for this curing time?
Dreadnaught Posted May 31, 2022 Posted May 31, 2022 It doesn't help you, but when I asked the concrete team that poured my raft when my concrete would finish setting, they said 40-years . There's some truth in that.
Mr Punter Posted May 31, 2022 Posted May 31, 2022 It is worth keeping it covered for at least a week, especially if is windy, warm or in the sun.
Conor Posted May 31, 2022 Posted May 31, 2022 Long weekend should do the trick. You'd want to keep any serious point loads off until 28 days, that's normally the design strength.
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now