Taya McKinnon Posted April 26, 2022 Posted April 26, 2022 Hi, I'm hoping someone can help. We are having a two storey rear extension being done. Our bricklayer has done a vertical dpc on the second lift but not on the first?? Should the vertical dpc have been done on the first lift as well as the second?
markc Posted April 26, 2022 Posted April 26, 2022 1st and second lift? Brick courses? Stories? And are you talking about a movement joint?
Taya McKinnon Posted April 26, 2022 Author Posted April 26, 2022 Should there be a vertical dpc running between the inner and out skin all the way down the building to the dpc along the bottom of the building?
ETC Posted April 26, 2022 Posted April 26, 2022 DPC and insulation required at the junction of the new and old wall constructions. Normally wall starter kits used or full cavity opened so that the cavities and insulation is continuous. 1
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now