January 14, 20224 yr I got a call from Green Building Store today about delivery of my MVHR unit next week. I mentioned I was surprised as I thought there was a 6 month lead time on them as I wasn't expecting it for a few more months. To which he said that they're currently on a 40 week lead time. I was so shocked I nearly fell off the scaffolding. Glad I got in there early then. So, if anyone is thinking of going for a Zehnder unit then they'd better get it ordered well in advance.
January 14, 20224 yr 9 minutes ago, Thorfun said: I got a call from Green Building Store today about delivery of my MVHR unit next week. I mentioned I was surprised as I thought there was a 6 month lead time on them as I wasn't expecting it for a few more months. To which he said that they're currently on a 40 week lead time. I was so shocked I nearly fell off the scaffolding. Glad I got in there early then. So, if anyone is thinking of going for a Zehnder unit then they'd better get it ordered well in advance. Good tip
January 14, 20224 yr I've got a spare Roda Spa Asym electric in matt black for sale. Has a very slight mark in the corner but other then that brand new, never been fitted.
January 14, 20224 yr Author 6 minutes ago, SuperJohnG said: Is this just affecting Zehnder? Or seeing the same issues with vent axia etc? I don't know, sorry. the last time I spoke to our M&E company they specifically said Zehnder but it might be only because that's the unit we're having and when I spoke today I didn't ask about other manufacturers.
Create an account or sign in to comment