MikeGrahamT21 Posted September 21, 2021 Share Posted September 21, 2021 So applied for planning last year, but wasn't ready to build til this year at earliest, and then the lack of builders put that to bed. I'm hoping to get going next year, but if for whatever reason that doesn't happen, that gives me a year left until i need to pay the council some more ££ which i'd rather not do if I can help it. There is some timber cladding which was part of the planning permission, and I'm wondering if doing a section of that which can be completed would constitute as build commencement? Otherwise what else can I do? Dig a hole which would form part of the foundations? All ideas welcome! Hoping this doesn't become an issue in reality tho Link to comment Share on other sites More sharing options...
Temp Posted September 21, 2021 Share Posted September 21, 2021 https://www.fsp-law.com/planning-permission-and-commencement-of-development/ What constitutes “commencement”? In order to lawfully ‘commence’ development it is necessary to satisfy the legal requirements in section 56(4) of the Town and Country Planning Act 1990. This says that “development is taken to be begun on the earliest date on which a material operation is carried out”. A material operation can include any works of construction, demolition, digging foundations, laying out or constructing a road and a material change in the use of the land. In practice, very minor works are usually sufficient to commence development. This could be as simple as putting in footings or even just pegging-out a roadway. Caution should be had though, as any works done must reflect what was actually permitted by the planning permission. This means crucially that any pre-commencement planning conditions must be complied with before works commence on site. Otherwise any works done to implement in accordance with section 56(4) may not be lawful and may then be subject to challenge by the local authority. If the planning permission contains ‘pre commencement’ conditions which are not likely to be complied with before the date on which the planning permission would (but for implementation) expire, then in the alternative an application could instead be made to vary the planning condition. This could be dealt with by way of a s.96a application (an application for a non-material amendment) to vary the wording of the relevant conditions to perhaps delay the date for compliance. The CIL risk Commencing development has become an even hotter topic in light of the Community Infrastructure Levy (“CIL”) because commencement of development triggers the requirement to pay any CIL. It is important to note that the CIL regulations also provide that before commencing development, a valid ‘Commencement Notice’ must be submitted. Crucially, such a notice must be in the form required by the regulations and so a simple email to the local authority will not suffice. Historically, failure to serve such a notice prior to commencement would have also resulted in any reliefs or exemptions from CIL being lost: this is no longer the case, but new surcharges do apply. Some councils will tell you what they require you to do. In some cases this is digging foundation trenches, getting them inspected by Building Control and filling them. The problem is that you have to pay a fee to Building Control to get started and some will close a file if progress seems to have stopped. If the council won't tell you then it is possible to do some work and apply for a certificate of lawfulness to determine you have officially started. Wind farm developers sometimes do this while they wait for the grid to be upgraded. Problem is the fee. 1 1 Link to comment Share on other sites More sharing options...
MikeGrahamT21 Posted September 21, 2021 Author Share Posted September 21, 2021 Hmm OK, may be worth an email to the council. I’m hoping it doesn’t come to this, still a good 18 months to go yet, but time soon flies! Link to comment Share on other sites More sharing options...
Mania Posted April 11, 2022 Share Posted April 11, 2022 HI Mike How did you get on? What did you have to do? We are in a similar situation wanting to get commencement signed off / acknowledged by the council. Link to comment Share on other sites More sharing options...
Temp Posted April 11, 2022 Share Posted April 11, 2022 ping @MikeGrahamT21 Link to comment Share on other sites More sharing options...
MikeGrahamT21 Posted April 11, 2022 Author Share Posted April 11, 2022 Hi, I’ve managed to find a builder, though at present they haven’t started yet (were due beginning of month but are behind) so I’m hoping that this won’t be an issue for me as currently I’m not well enough to do any digging. sorry can’t give any more help. Mike Link to comment Share on other sites More sharing options...
Mania Posted April 11, 2022 Share Posted April 11, 2022 7 hours ago, Temp said: ping @MikeGrahamT21 thank you @Temp Link to comment Share on other sites More sharing options...
Mania Posted April 11, 2022 Share Posted April 11, 2022 No problem @MikeGrahamT21 Thank you for responding. I hope you feel better soon. I'll do some digging around 😉 1 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now