Moonshine Posted March 11, 2021 Share Posted March 11, 2021 To shortern our progress on site i am looking to get my br application in. The issu is that we don't have planning approved for a revised scheme, due end of this month, with hopeful no pre commencment condition to discharge. I don't think the planners will want any changes but I presume I can tweak the br drawings before approval. Anything I am missing? Link to comment Share on other sites More sharing options...
Bonner Posted March 11, 2021 Share Posted March 11, 2021 In my experience, there is no connection between planning and building control. We are using a neighbouring LA for building control. I considered going for BR before planning and my architect advised it would be fine. Only consequence of changes would be that I would have to pay them more money to revise the drawings ? The risk is on you, potential costs if there are any changes needed. Link to comment Share on other sites More sharing options...
Moonshine Posted March 11, 2021 Author Share Posted March 11, 2021 (edited) 9 minutes ago, Bonner said: Only consequence of changes would be that I would have to pay them more money to revise the drawings ? The risk is on you, potential costs if there are any changes needed. I have done the drawings so it's only my time I would waste. Just waiting on the structural engineer then for their drawing package, and I will get them submitted. Edited March 11, 2021 by Moonshine Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now