Jump to content

Tony L

Members
  • Posts

    255
  • Joined

  • Last visited

Personal Information

  • Location
    Surrey

Recent Profile Visitors

The recent visitors block is disabled and is not being shown to other users.

Tony L's Achievements

Regular Member

Regular Member (4/5)

60

Reputation

  1. Thank you for starting this thread off @Canski. I was thinking BCO & warranty inspector would do all the necessary inspections as the build progressed, & the SAP guy would have a quick look at the end & do some sums based on information I provided. I expected the process would be no more arduous than the last time I got an SAP cert for my rental flat. I can see this is something else I need to have a good look at before work recommences on my project
  2. I can’t say for sure, yet. I had to ditch the Arch Tec whose drawings I already have, because they were so full of mistakes & he wasn’t good at correcting them, even though I was giving him plenty of help – so there’s no point in me telling you more about these drawings, because they didn’t reach the stage where I was ready to get the SE involved in the superstructure calcs (my foundations are already built). I engaged a new Arch Tec & paid him (on 19 May) & I haven’t seen a single drawing from him yet, even though I was supposed to have a full set of draft drawings at the beginning of July. Yes, I’m annoyed with him, but I’m still expecting his work to be good quality when I eventually see it. When I get the new drawings, I’m envisaging my thick wall, with the blocks laid flat, will run up to the height of the first floor, then there’ll be upright blocks on top of this, flush with the wall beneath on the side with the stairs, & running all the way up to the vaulted ceiling/roof. If the SE looks at the drawings & says we need to make a change, & go all the way up with the blocks laid flat, I don’t think this will create too much extra work for the Arch Tec. I’d rather keep to upright blocks at first floor level, as blocks laid flat would eat up an extra 115mm of bedroom width, & cost more.
  3. I thought so too then I did a bit of Googling & found this review, which has made me wary.
  4. Yes, I'm interested. Thanks for posting these. These diagrams assume a zinc roof (formed on site), so I'm not sure they answer all the questions you may have if you end up going with Pagurek click system, as you suggested you may do, in a recent post. Please keep us all updated, as you work towards your solution.
  5. I don't want my garage to be completely airtight, but I was thinking, if it was a lot more airtight than most garages then I could run a PIV in there to pressurise the room & dry out the cars when they need it - some of my cars are old & may be left for weeks at a time without being used. Also, I might heat the garage if I'm working on one of the cars during the winter. I have the PIV that was rescued from my bungalow before it was demolished. I'm thinking the best solution may be to have a regular garage door, for security, then some king of curtain arrangement inside to increase the air tightness.
  6. No, but I'm planning this (that's if I have any money left when the build nears completion). I discussed my plan with my SE, & my drawings show standard 7N blocks laid flat - so my wall that the stairs will hang off is 215 thick (+ finish) rather than 100.
  7. These were my first thoughts. If you've identified an affordable, reasonably airtight garage door, I'd be interested to hear about it, please.
  8. Just confirming AeroBarrier is indeed zero rated for new builds. & their responses to two emails I sent were very helpful, although they weren't prepared to say, "If we come along & your building is already at x ACH, we'll guarantee to get it down to 0.6 or better.". That's not a big surprise really, although a guaranteed result would certainly mean I'd be more likely to go ahead with them.
  9. There are different ways of dealing with this problem & each way carries different risks. If it were me, I’d be saying he’s broken the contract because he didn’t, “provide a high quality outcome for the works”, (that’s a quote from your contract), so there’s no reason the client should be bound by a contract that the builder broke; he’s off the job, & he’s not getting any more money. If you want to carry on fulfilling your side of the contract, so the builder has no opportunity to say you’re in the wrong then you need to write to him, if you haven’t done so already, to tell him the work is no good. Just two or three sentences should be enough. Do not mention anything he’s done wrong other than the Posis & the steels – you don’t want to give him the opportunity to argue, at length, over some trivial matter. It’s highly unlikely he will order, pay for, & wait for delivery of a full set of Posis & steels, & have them all installed & looking as they should do, within 14 days of receipt of your email/letter. & if he tells you he's going to fix his work, as @saveasteading says, you should insist on a formal proposal for a schedule of the remedial works, so he'll have that to squeeze into his 14 days timeframe as well. Also, your contract says mediation should take place. Your contract isn’t specific about the kind of mediation, so this would just need to be a short meeting with you, the builder & a mediator – it doesn’t even matter if the builder chooses the mediator – you don’t have to agree to the mediator’s suggestions. So if you want to still be seen to be upholding your contractual obligations (even though he broke the contract), email him to offer mediation, at your site, one day this week. As I say, if it were me, I'd not be even giving him these opportunities.
  10. Good luck, @Nick Laslett, & thanks for your airtightness details. You certainly sound as though you know what you're doing, so I have saved a copy of your post in my "Airtighness" folder, which I will hopefully remember to look at when I start to select (or others start to propose) which products will be used in my build.
  11. I should think you're right. Email sent. I'll report back.
  12. I'd worry about my lungs. Do the AeroBarrier team zero rate their invoice, @Nickfromwales?
  13. Don't say this until you know the cost of correcting the work is a lot less than the amount he's going to say you owe him. If he's going to get nasty with you, your starting point for negotiation should be: He's broken the contract, by consistently undertaking poor quality work & overcharging, so you're going to force him to pay a competent builder to undertake the required remedial works, because he has demonstrated over the course of several weeks, he's incapable of doing the work to an adequate standard himself.
  14. Well done. You're managing this situation well. Keep us updated. I'm following with interest, as I had similar problems with my first builder (& I'm still only just out of the ground with my build). I also had to defend myself against threats from his solicitor, so don't be surprised or concerned if that's your builder's next move. He will concede once he realises that you're more capable & robust than his usual clients.
  15. Congratulations. That looks like a splendid location. I'm looking forward to hearing more, as work progresses.
×
×
  • Create New...