Can anyone offer me some advice on the best way to build up my floor level for UFH installation?
I have removed the old suspended timber floor on the ground floor level as it was rotten, I now have a void of 330mm to fill to make up the floor level.
The house has a concrete base level which runs all the way through already.
I had planned to use some hardcore then soft sand, Damp proof membrane then insulation and UFH screed. but the building inspector did not like this plan and said he wanted me to pour more concrete in before adding insulation.
So now I am thinking off levelling off the existing concrete damp proof course, then adding 260mm of insulation, then finish off with 70mm of screed and UFH pipes.
Does this make sense? or can anyone suggest a better method?
Thanks