3: Site Scrape and Setting Out
Yesterday (August 21st 2018) the ground workers arrived at 07:00 to scrape the site, erect some Heras fencing and mark the house out.
The engineer did the setting out first of house boundary.
Next the digger driver and one ground worker scraped the site.
Next the engineer marked out where the foundations should go, ready to be dug tomorrow.
The digger also ripped up the old tarmac road that ran through the plot.
They finished at 18:00