Mulberry View Posted 1 hour ago Posted 1 hour ago I have a UFH design, done by the company who'll be doing the screeding. They are able to supply quality components without the mark-up the likes of Continal et al enjoy. But what of the Supply and Return pipes for the manifolds? We haven't bottomed out an ASHP design yet and ideally would prefer to kick this can a little further down the road if possible. Is it normal for these pipes to be placed in the screed to be considered later? There is a manifold in the Utility Room, very close to the ASHP (no need for buried pipes?), plus one in the Kitchen and a possible third one for the first floor (I can't imagine that needs considering in the ground floor screed).
Nickfromwales Posted 1 hour ago Posted 1 hour ago Why 2x manifolds? Just done 16 ports here, same manifold location, so doubt you need to spend out on the second setup.
Nickfromwales Posted 1 hour ago Posted 1 hour ago Sorry, 28mm pipes to the manifolds, which can be set into the top of the insulation.
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now