boxrick Posted Monday at 20:44 Posted Monday at 20:44 Hello folks. A simple question, my plasterer is booked in. There is still a lot of boarding to do. Simply put should I get a room plastered whilst still fitting boards in other rooms? Or will the dust ruin my finish?
bmj1 Posted Monday at 21:12 Posted Monday at 21:12 Just put up dust sheets if worried about dust - and crack on. Good to make headway with plastering as it takes time to dry out - which is your bigger challenge than dust control and hoovering.
Oz07 Posted yesterday at 07:18 Posted yesterday at 07:18 dust wont be a problem have you seen the dust they create when mixing gear. Is he on price though as might have the ump if not 100% ready to go at. Don't slow them down