Crofter Posted Monday at 22:50 Posted Monday at 22:50 11 hours ago, Nickfromwales said: Never disconnect panel strings in sunlight or under any load, and they need to be the last thing shut down. For an off grid system the order is disconnect panels before batteries. I've killed an MPPT by getting that one wrong.
Nickfromwales Posted Monday at 22:51 Posted Monday at 22:51 Just now, Crofter said: For an off grid system the order is disconnect panels before batteries. I've killed an MPPT by getting that one wrong. Thanks for the info. It'll be useful to the OP. 1
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now