Self Commissioning


Recommended Posts

Have most people here who installed their own systems also handled the commissioning themselves? I'm almost finished running the last few ducts and am starting to think about the next steps.

 

My main question is about measuring the flow rate. If I can get my hands on an anemometer, do I simply divide the total flow rate by the number of intake or exhaust valves to calculate the flow per valve?

 

Link to comment
Share on other sites

1 hour ago, Marko said:

If I can get my hands on an anemometer, do I simply divide the total flow rate by the number of intake or exhaust valves to calculate the flow per valve?

 

There's some useful DIY info at the start of this thread (plus a currently very short queue to hire, if that's of interest).

 

There's more to it than dividing the total by the number of valves, as you also need to take into account building regs flow rates for things like kitchens and bathrooms.

Link to comment
Share on other sites

On 21/11/2024 at 11:30, jack said:

 

There's some useful DIY info at the start of this thread (plus a currently very short queue to hire, if that's of interest).

 

There's more to it than dividing the total by the number of valves, as you also need to take into account building regs flow rates for things like kitchens and bathrooms.

 

Thanks Jack, I've gotten my head around the requirements now. I'd be very interested in hiring the anemometer. Do you have any ideas of timescales so we have something to aim for in terms of getting the last ducts ran?

Link to comment
Share on other sites

 

6 hours ago, Marko said:

Thanks Jack, I've gotten my head around the requirements now. I'd be very interested in hiring the anemometer. Do you have any ideas of timescales so we have something to aim for in terms of getting the last ducts ran?

 

It's highly variable, but two or three weeks is a pretty common turnaround time (per hire).

 

There's only one person on the list in front of you at the moment. I'll add you to the list. If you're not ready when you're up, let me know and we'll skip to the next person on the list (if there is one by then).

Link to comment
Share on other sites

1 hour ago, jack said:

 

 

It's highly variable, but two or three weeks is a pretty common turnaround time (per hire).

 

There's only one person on the list in front of you at the moment. I'll add you to the list. If you're not ready when you're up, let me know and we'll skip to the next person on the list (if there is one by then).


Fantastic. Very much appreciated! 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...