MechanicalBuilder Posted June 20, 2024 Share Posted June 20, 2024 Evening all, has anyone ever had any issues getting their as built saps and completion certificate when cascading ASHP without prior planning permission? I’m planning on attempting it with my self-build and I’ll have installation and commissioning certs. Permitted rights only allow one ASHP but im looking to install 2. Is anyone likely to look into this when I obtain my as built saps and then completion cert? Link to comment Share on other sites More sharing options...
JohnMo Posted June 20, 2024 Share Posted June 20, 2024 Obvious question is why would a new build need two ASHPs? Unless your building a large mansion. Permitted rights do not exist, while a property is being build under planning permission. So everything should be under on approved drawings. Link to comment Share on other sites More sharing options...
Conor Posted June 22, 2024 Share Posted June 22, 2024 (edited) We moved our ASHP and just included it in an NMA application with some other tweaks, I'm sure you could try the same. Edited June 22, 2024 by Conor Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now