benben5555 Posted November 2, 2023 Share Posted November 2, 2023 Hi Guys, I've got a 6.6m x 6.2m reinforced concrete slab to go down in the garage, on top of the beam and block floor, 100mm thick. To avoid future cracks do I need to include a movement joint? Or a crack control joint? I was thinking about laying in two bays, but that would take more time and cost more. Any thoughts? Link to comment Share on other sites More sharing options...
markc Posted November 2, 2023 Share Posted November 2, 2023 At 6x6 put it down in one go 1 Link to comment Share on other sites More sharing options...
Conor Posted November 2, 2023 Share Posted November 2, 2023 If you've mesh it'll be fine. 1 Link to comment Share on other sites More sharing options...