Welsh-border Posted March 22, 2023 Share Posted March 22, 2023 I have to connect my foul water drainage to the treatment plant. What do I need to put in place where the 2 pipes exit the foundations A + B : a) to satisfy building regs b) ease of access. Can I just join A and B and then a single pipe to the treatment plant or should I take both pipes to a point near the treatment plant? Thanks Link to comment Share on other sites More sharing options...
Conor Posted March 22, 2023 Share Posted March 22, 2023 Inspection chamber at both and run A in to B then single run to the treatment plant. Link to comment Share on other sites More sharing options...