July 27, 20179 yr Approaching the end of the project and therefore the budget! We have 70 Dow lights to second fix, with circa 30 other lights. 60 double sockets? A weeks work? Two weeks?
July 27, 20179 yr I allow 1 our per point for first and second fix, and it's usually less than that. So 160 points is probably 80 hours work for second fix, so 2 weeks.