Jump to content

Breaking up and relaying concrete slab


CambridgeMart

Recommended Posts

We've bought a new property which has a 10m x 7.5m barn; the barn was originally a cowshed and milking parlour and has a concrete floor which is very uneven, has drainage channels and large holes in it. We will be using the barn as a garage and workshop; it needs the floor relaying and I will be incorporating insulation in the slab as the temperatures get down to -40C in winter! The slab needs breaking up and digging out and a new slab pouring; we have had quotes from local construction firms and the quotes were astronomical, so we plan to do this ourselves.

Presumably an excavator with a breaker attachment is the way to go, can anyone suggest how long we should hire it for (I've hired diggers, but never used a breaker attachment before)?

Link to comment
Share on other sites

Do you really mean -40°C..??!!

 

75sqm of concrete - which is probably 150mm or more thick - will take a lot of work. You’ll need a 5 tonner with pecker on it and it will take 2-3 days of work to break that lot up and then the same to clear it. You’ve then got a lot of concrete to get rid of….

 

Your other issue may be that there is reinforcing mesh in the slab. That will be a problem for both breaking up and removing.
 

If it is a barn - and you have the height - then I wouldn’t be removing the current deck. I would be looking to fill the holes, edge with a row of blocks and then overlay with 100mm of insulation and then go with mesh on chairs and top with concrete.
 

You can easily build up a ramp to take the 200mm or so of the new slab and tbh it will be much cheaper than taking it out and the difference will be negligible. I would say though unless you’re going to sort walls and the roof then insulation in the floor is going to be an expensive folly !!

Link to comment
Share on other sites

Yes, -40C (this is in Northern Finland); we don't believe there's any reinforcement in the slab. Pouring on top of the existing slab sounds attractive, I need to check that the current garage doors height will still be sufficient if we raise the floor level; that may also limit the machine I hire, a 5 tonner is quite high.

I suspect that the building contractors are covering their behinds by quoting for a completely new slab so they can be 100% certain of no future issues; I am not worried if a few cracks appear somewhere down the road!

Yes, we are (heavily) insulating the barn and installing heating, after all my new man-cave needs to be cosy!

Link to comment
Share on other sites

We pulled up around 500m² of agricultural slab in just over a week with a 5T excavator, pecker and a 1T dumper.  We were slowed down by a reinforced perimeter ring-beam that had 30 - 40mm rebar in it and had to cut the rebar into manageable lengths.

 

image.thumb.png.c3dbd9a4fbd1c86d29e059958bf25549.png

 

Ours was also a cowshed, so had a significant rake on the slab for slurry drainage. We'd have lost a lot of height to have mass infilled over the top and then insulated.

 

The 5T machine broke it up quickly. I did other channels through hard-standing areas with a 1T, and that was hard going.

Link to comment
Share on other sites

The garage doors are 1800mm high, adding 200mm to the slab may cause us a problem with clearance; it's probably a toss up whether we increase the slab height by 200mm and raise the aperture for the door by the same amount, or go with plan 1 and break up the original slab and re-pour it.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...