Adsibob Posted October 6, 2021 Share Posted October 6, 2021 55mm to 60mm of sand and cement screed is being poured over my UFH pipes/insulation on Friday. The floor finish will be microcement poured onto the screed - that is only 3.5mm thick. I need to lay a power cable under the floor finish so that the kitchen island has power. What's the best way of doing this given all the 16mm UFH pipes that will be in the way. Should I lay a duct in case the cable ever needs to be replaced? - though can't see why that would be the case Link to comment Share on other sites More sharing options...
markc Posted October 6, 2021 Share Posted October 6, 2021 Definitely in a duct 1 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now