Barryscotland Posted July 13, 2021 Posted July 13, 2021 We need to take delivery of our attic trusses a month before we need them to avoid another increase in the price of them. There 9m long an there’s 45 of them. I was thinking of cementing a couple of scaffold poles into the ground and making a frame of scaffold to support them. Any ideas / advice appreciated
PeterW Posted July 13, 2021 Posted July 13, 2021 See if anywhere local has any forklift stillages lying around. Three in a row on a few blocks or hardcore could be leveled to keep them off the ground.