Morning, the slab concrete has been laid over the rebar and we took 5 samples of the concrete as it was delivered. Do I really need to send these off for testing?

 

Cheers Everyone. 

Posted

Unless the slab will be subjected to some very high point, pull-out  or bending loads (large cantilever) then no reason for testing.

  • Like 1
Posted
1 hour ago, hallega said:

SUPER...... I shall use them as door stops then! Cheers. 

If you have them, its a good idea to keep them for a while in case of future problems - very unlikely but sample cubes make good evidence.