Wagas Posted November 20, 2019 Share Posted November 20, 2019 I'm a bit tight on time and wondering what the minimum time a new UFH system should run for before any floor coverings go down? Specifically LVT and porcelain tile. Floor is extra strength liquid screed mostly 40mm but some areas 50mm. Screed went down end of September. Thanks Link to comment Share on other sites More sharing options...
nod Posted November 20, 2019 Share Posted November 20, 2019 I ran ours for a week 24 7 started at 20 and cranked up a couple of degrees per day Then I turned the boiler off and let it cool down overnight Then laid the matting 150m2 Then laid the porcelain over the next four days Link to comment Share on other sites More sharing options...