I had gone with MBC for the package and foundations but having had a bad ground investigation report MBC say the site needs piling and they can't adapt their insulated raft design for piles. I need to get the foundations redesigned independently which is annoying as I wanted a foundation/frame package that would get the structure up quickly. AFD will design but don't do the work and I have also asked Abbey Pynford who have pile and foundation package to quote but don't yet know what u-value they can achieve. Has anyone any experience of their Comdeck system ?
Hi
Just joined up after recommendation from another self builder. We've got planning for a house in Wiltshire for us to downsize into. This will be 4th new build, the last one 20 years ago - after which I swore I'd never do another one !