Hello all,
apologies if a similar question has been raised in the forum. I did search extensively beforehand.
For my house extension, we have decided to add a basement.
The original plans that the structural engineer created, stated that the outside walls of the basement were to be made using blockwork.
The structural engineer made site visits in advance of the original plan.
This plan was used for tendering and the basement company we choice, estimated according to the original SE plan.
During further discussions between the SE and the basement company, the outside walls are now to be made of reinforced concrete.
This redesign has increased the costs of the basement significantly.
Nobody informed me of the increase in costs that this change would cause until shortly before the basement works started, leaving me with no option but to proceed with the basement.
I am now in dispute with the structural engineer over this matter.
I have a few questions:
1. Am I right to point the finger at the SE?
2. What are my options?
3. Would I be within my rights to withhold any due invoices towards the SE until this matter is clarified?
Thank you all in advance!